NLLD Projects Completed 2016 – 2021

(updated April 8, 2021)

Mathews Canal/Clotilda Levee Improvements Project

Project Area: Gheens,  Project Cost:  $,  Date Comp

Des Allemands Bulkhead Project

Project Area: Gheens,  Project Cost:  $,  Date Comp

Jesse Dufrene FDA Levee Improvements

Project Area: Gheens,  Project Cost:  $,  Date Comp

80 Arpent and Halpin Canals, East Theriot Canal, Sam Foret and adjacent canals Maintenance Dredging Project

Project Area: Lake Bouef Watershed,  Project Cost:  $,  Date Comp

Lockport-Larose Reach B-2 Access, Levee, and Culvert Repair

Project Area:  Lockport-Larose,  Project Cost:  $,  Date Comp

Parr/Larose Pump Station 30” Pump Addition and Canal Debris Screen

Project Area:  Lockport-Larose,  Project Cost:  $,  Date Comp

Crest Pump Stabilization

Project Area:  Thibodaux-Lockport-Bayou Blue,  Project Cost:  $,  Date Completed:

U.S. 90 at Bayou Folse

Project Area:  Thibodaux-Lockport-Bayou Blue,  Project Cost:  $,  Date Completed:

Lockport to Larose Valentine Return Levee

Project Area:  Lockport-to-Larose,  Project Cost:  $,  Date Completed:

Des Allemands FDA Levee

Project Area:  Gheens,  Project Cost:  $,  Date Completed:

TLBB EL No. 2 Coastal to Twin Oaks Phase 1

Project Area: ,  Project Cost:  $,  Date Completed:

40 Arpent and 80 Arpent Canal Maintenance Dredging

Project Area:  Lake Boeuf Watershed,  Project Cost:  $,  Date Completed:

East Theriot Canal ROW Maintenance Dredging*

Project Area:  Lake Boeuf Watershed,  Project Cost:  $,  Date Completed:

*Maintenance Project

Sam Foret Canal ROW Maintenance Dredging

Project Area:  Lake Boeuf Watershed,  Project Cost:  $, Date Completed:

Zeller/Larousse Forced Drainage – Phase 1A Clearing and Dredging

Project Area:  Lake Boeuf Watershed,  Project Cost:  $,  Date Completed:

Lockport to Larose Valentine Return Structure 

Project Area:  Lockport-to-Larose, Project Cost:  $, Date Completed:

St. Charles By-Pass Backwater Flooding

Project Area:  Thibodaux-Lockport-Bayou Blue, Project Cost:  $, Date Completed:  

Lockport to Larose Reach D3

Project Area:  Lockport-to-Larose, Project Cost:  $, Date Completed:  

Lockport to Larose Reach A2 Levee & Claudet Levee Lift Project

Project Area:  Lockport-to-Larose, Project Cost:  $, Date Completed:

Lockport to Larose West Side, Reach A1 Levee

Project Area:  Lockport-to-Larose, Project Cost:  $, Date Completed:

Lockport to Larose West Side, Reach D2 Rip Rap Armoring

Project Area:  Lockport-to-Larose, Project Cost:  $, Date Completed:

Bayou Rond Pom Pon

Project Area:  Lake Boeuf Watershed, Project Cost:  $, Date Completed:

Rienzi Drainage Area Study/Leighton Drainage Area Study

Project Area: Regional, Project Cost:  $, Date Completed:

South Thibodaux Drainage Project

Project Area:  Thibodaux West, Project Cost:  $907,919.25, Date Completed:  September 2017

Parr Pump Station Improvements

Project Area:  Lockport to Larose, Project Cost:  $283,524.00, Date Completed:  June 2017

Levee Repairs –Bayou Dumar at Hwy 653

Project Area: Thibodaux – Lockport – Bayou Blue, Project Cost: $63,521.58, Date Completed:  May 2017

80 Arpent West Right-of-Way Clearing and Maintenance Dredging

Project Area: Choupic, Project Cost: $504,997.33, Date Completed:  May 2016 

80 Arpent East Right-of-Way Clearing and Maintenance Dredging

Project Area: St. James, Project Cost: $505,339.81, Date Completed:  May 2016